Figure 34: Connecting Bridge to Northern Road at Project Site
The ongoing bridge connection works is seen in Figure 34. The current
Municipal bridge that crosses across the Noyyal River, is to bifurcate and a
road is to develop along Northern front of the site abutting the Noyyal River.
This proposed road under construction is a 2-way road, and this has been
factored into the design.
The image below, Figure 35, indicates the large expanses of unused
agricultural land in the middle of the project site. Most of Tiruppur was largely
agrarian as discussed, until the textile industry boom in the 1980s.